Day 1

  • Remove shower (if remodeling/replacing)

  • Shim and plane studs to ensure all surfaces flat and square.

  • Ensure proper studs/blocking for eventual frameless glass hinges.

  • Move any plumbing if needed

Day 2

  • Install Kerdi board on all to-be tiled surfaces (except floor)

  • Install Kerdi shower pan system or PVC liner and custom dry-packed shower floor

  • Ensure all seams are bonded and fasteners are waterproofed

Day 3

  • Plug drain and perform a 24-hour waterproof test.

  • We will flood the shower pan, and monitor for any leaks to ensure a waterproofed shower before we begin tiling

Day 4-5

  • Plan layout and approve with owner

  • Install tile on shower walls (except for first row)

Day 6

  • Finish walls as needed

  • Install tile on shower floor

Day 7

  • Install shower first row of wall tile

  • Install grout on all tile

Day 8

  • Install quartz thresholds if needed.

  • Caulk and cleanup.

Day 9

  • Measure for frameless shower glass

  • Lead time is approximately 2 weeks for glass to be manufactured and installed

Complete

  • Approximately 2 weeks later your shower glass will be installed.

  • Time to enjoy your beautiful new shower!